TeraWulf executed a definitive EPC agreement with Fluor for the construction of three data center buildings at its Justified Data Campus in Kentucky, supporting a $19 billion lease with Anthropic. Additionally, Google LLC entered into credit support agreements to backstop Anthropic's lease obligations, significantly strengthening the project's financing profile.
TeraWulf Inc. entered into amended agreements with Kentucky Power to double the contracted power capacity at its Muskie Data Campus from 500 MW to 1 GW. The agreement also accelerates the delivery timeline for the second 500 MW phase from 2030 to 2029 to meet high customer demand for AI and high-performance computing infrastructure.
Counterparty
Kentucky Power Company
Term
through 2029
“Customer interest in Muskie has been tremendous, and power availability is central to those conversations. Securing the next 500 MW and moving its planned delivery into 2029 gives us greater flexibility to meet prospective customers’ deployment needs.”
Paul Prager, Chairman and Chief Executive Officer of TeraWulf