Net Power Capacity Expansion
Net Power Inc. entered into an agreement with Saulsbury Industries to extend the deadline for delivering a full notice to proceed (FNTP) for its utility-scale project from October 2026 to March 31, 2027. The extension allows more time to negotiate a post-closing change order and a limited notice to proceed (LNTP) for the project's EPC agreement. If the company fails to execute the LNTP by November 15, 2026, it must pay a $3.5 million termination fee.
- Counterparty
- Saulsbury Industries, Inc.
- Term
- through March 2027